How a new turnkey lift is delivered
Under standard conditions, the completion time for the entire work "ON KEY" is 3 to 4 months from the signing of the
contract.
contract.
1
Visit to the customer and measuring of the lift (or taking all the information necessary for the preparation of the initial study and indicative price proposal).
2
Preliminary discussion of the project with state institutions (building authority, sanitation, fire brigade, monuments, etc.).
3
Meeting with the customer to select and determine the design of the elevator from the submitted samples.
4
Preparation of a price offer and commercial and technical documentation including an indicative layout drawing of the elevator. The price offer also includes conditions for subsequent service.
All of the above activities are, as a rule, carried out without obligation and free of charge
5
Signing the contract for the work
6
Preparation of complete project documentation
7
Negotiating and securing a building permit
8
Commencement of installation including:
- Elevator shaft construction (if part of the work)
- Installation or assembly of the lift
- All construction work
9
Before commissioning:
- Commissioning of the lift
- Testing by an authorised person
- Carrying out noise tests
- Obtaining the approval decision
10
Handing over the work
SEE WHAT THE NEW LIFTS LOOK LIKE
Orona lifts are beautiful and practical. Lifts can be colourful or subtle, but they are always functional and reliable.
+ 3
New passenger lift, glass shaft in staircase, Prague 1, New Town
+ 1
New passenger lift, glass shaft from the courtyard, Prague 6, Holesovice
+ 1
New passenger lift, glass shaft from the courtyard, Prague 6, Bubeneč
+ 1
New passenger lift, glass shaft from the courtyard, Prague 3, Vinohrady
+ 0
New freight elevator, 4000 kg, Prague 10, Dolní Měcholupy
+ 3
New freight elevator, 4600 kg, Prague 10, Dolní Měcholupy
+ 6
New passenger lift Orona, glass shaft in the staircase mirror, Prague 9, Libeň
+ 2
New passenger lift, Argentinská Street, Prague
+ 3
New passenger and freight elevator, Bulovka, Prague
+ 5
New passenger lift, Hollarovo Square, Prague
+ 1
New passenger lift, Jinonická, Prague
+ 2
New passenger lift, Odborů, Prague
+ 8
New passenger lift, Plzeňská, Prague, load capacity 630 kg
+ 1
New freight elevator, Revoluční, Prague
+ 1
New passenger lift, Slezská, Prague
+ 1
New passenger and freight elevator, SOU Kladno
+ 1
New passenger lift, Tesnov, Prague
+ 1
New passenger lift, Tyršova, Prague